The Right Location For Data Center Development 

Crossroads Technology Campus will be a thoughtfully sited, state-of-the-art, data center campus. The site is already surrounded by existing commercial and industrial uses and will have an unprecedented 66% of green space and extensive buffers. It is the right location for the County.

Economic Gamechanger

The Crossroads Technology Campus will be an Economic Gamechanger for Spotsylvania County.

$37M

per year


Once completed, the campus will generate over $37 million per year in tax revenue to Spotsylvania County.

700+

permanent jobs


Upon build-out, the campus will support more than 
700 permanent jobs, 
including 226 on-site jobs.

25

years


The project is expected to generate nearly $1 billion in net fiscal benefit to Spotsylvania County over 25 years.

$635M

Over 25 Years


We project to generate more than $635 million in personal property tax revenue over the 25-year analysis period.

Sustainability Leader

Crossroads Technology Campus will be a leader in sustainability preserving approximately 66% of open space, using little drinking water and utilizing Tier 4 generators.

66%


An unprecedented approximate 66% of the site will remain as open space.

No drinking water

No drinking water will be used to cool the data centers. The campus will use only reclaimed water for cooling purposes.

300ft Buffers

The project will include 300-foot vegetated buffers and 400-foot setbacks between data center buildings and nearby homes.

Noise reducing enclosures

The backup generators used meet stringent, EPA Tier 4 emissions standards and include noise-reducing enclosures.

Prioritizes Wetlands

The site design prioritizes minimal impact to wetlands and the campus retains 66% (437 acres) of undisturbed space.

FAQs

Item #1

Project History

July 2023

Comprehensive Plan amendment adopting data center policies

July 2024

Land acquisition

February 2025

Initial infrastructure plan submitted

March 2025

Data center guidelines development initiated

June 2025

Updated infrastructure plan submitted

December 2025

Data center guidelines approved

January 2026

Phase 1 site plan submitted

February 2026

Approval process updated to require a Special Use Permit

April 2026

Special Use Permit application filed

June 2026

Second Special Use Permit submission

July 2026

Third Special Use Permit submission